Work backward from approvals
Before a start date means anything, you need the approvals in hand: your condo association's sign-off if it requires one, and Fairfax County permits. The county handles condo alterations through commercial permitting, which is different from a house, so allow for that in your planning. We do not publish processing times because they vary.
Building logistics to confirm
- Elevator reservation and protection, and whether a freight elevator is available.
- Allowed work hours, and any quieter hours for demolition and tile removal.
- Loading area and parking for crew and deliveries.
- How debris leaves the building and where it can be staged.
- Insurance certificate and any contractor registration the association requires.
Rules vary by building, so ask your management office or board for the current versions in writing.
Water shutoffs
Many condo bathrooms have shutoff valves inside the unit, but some work requires shutting water to a riser that serves other units. That usually needs notice and coordination through the building. Find out early which valves serve your bathroom.
Order of work
- Selections finalized and materials ordered before demolition.
- Protection of hallways, elevator and floors.
- Demolition during allowed hours.
- Rough plumbing and electrical, then inspections.
- Waterproofing, tile, then fixtures.
- Glass measured after tile and installed near the end.
Inspections are fixed points in the schedule. Walls cannot close until rough-in passes, which is why we plan around them.
Neighbors
The noisiest days are demolition and tile removal. A short note to adjacent units with the expected dates goes a long way. If the bathroom stacks above another unit, let that neighbor know a remodel is happening so they can report any unexpected stain quickly.
Living there during the work
If the condo has a second bathroom, daily life continues with some inconvenience. If it is the only bathroom, plan where you will shower during the project before demolition day.
Townhouses
Townhouses in Reston clusters have fewer building logistics, but parking, debris containers and shared walls still matter. Your cluster association may have rules on dumpsters or work hours.


A sample planning timeline
- Consultation and written scope.
- Selections finalized; association application submitted with the scope.
- Permits applied for once the scope is set.
- Materials ordered and delivery date confirmed with the building.
- Neighbors notified and elevator reserved for demolition day.
- Work begins, with inspections scheduled at rough-in.
- Final inspection, glass installation and walkthrough.
We do not attach day counts to these steps because they depend on the association, the county and the scope. The order is what keeps a condo remodel from stalling.
What we need from you
A smooth condo remodel depends on a few things only the owner can provide: access to the unit on work days, a contact at the management office, copies of the association's renovation rules, and quick decisions on selections. If you will be away during the project, tell us how to handle access and who can approve small decisions.
We handle the rest: the written scope, permits for the work in our scope, insurance documentation for the association, inspections and coordinating deliveries with the building. Clear roles on both sides are the simplest way to keep a multi-unit project moving.
When something changes mid-project
Old buildings and older bathrooms sometimes hide surprises: a corroded shutoff, damaged subfloor under a leaking toilet, or a duct that never reached the outside. In a condo, some of those may involve common elements the association is responsible for. Our scopes explain how unexpected conditions are documented and priced, and when the association needs to be brought in, so a discovery becomes a decision rather than a stalled project. Keeping your management contact handy makes those conversations faster.
When should I contact my condo association?▸
Before you set a start date. Approvals, insurance certificates and elevator reservations all take lead time.
Will my neighbors lose water?▸
Only if the work requires shutting a shared riser. Many units have their own shutoffs; we confirm which valves apply.
How long will the remodel take?▸
It depends on scope and on inspections. We give a project-specific timeline with the estimate.